Lawyer for disputes with a developer in Almaty — we calculate the penalty and make them finish the job

Inspection of an apartment in a new building with a lawyer before signing the acceptance certificate
  • We calculate the penalty for each day of delay in handing over the building
  • We record defects at acceptance and secure their remedy at the developer's expense
  • We recover the overpayment when the actual and designed floor areas differ
  • The first consultation is free, and before signing the acceptance certificate it is especially important
New buildings

We handle disputes between shared construction participants and buyers against developers

We recover penalties for delay in handing over the apartment

We secure the remedy of defects or compensation for their cost

We challenge discrepancies in floor area and secure a recalculation

We assist with acceptance and termination of the contract when deadlines are missed

Civil lawyer Asel Kurmanova

Send us the contract and your correspondence with the developer — we will calculate the penalty and tell you what can realistically be recovered.

  • 14years
    real estate practice
    Shared construction, delayed handover, defects in the flat, unilateral termination of the contract.
  • 70+
    disputes with developers
    Cases against Almaty developers: penalty, rectification of defects, refund of amounts paid.
  • 6×
    difference between the offer and the amount recovered
    How much the court award is usually higher than what the developer offers voluntarily.
  • 0₸
    initial consultation
    We review the contract and the handover certificate and calculate the penalty from the exact date of delay.

Penalty for delay

The building was handed over later than the contractual deadline. We calculate the penalty for each day and recover it — usually many times more than the developer offers voluntarily.

Handover inspection of the flat

We attend the inspection and record defects in the certificate. A certificate signed without comments sharply narrows the options for a subsequent dispute.

Defects in finishing and works

Crooked walls, non-working ventilation, cold bridging, leaks. We demand rectification or compensation for the cost of works based on an expert examination.

Discrepancy in floor area

The actual area is less than the design area — recalculation and refund of the difference. If more — we check the lawfulness of the demand for additional payment.

Refusal to hand over the flat

The developer demands signing the certificate without comments or paying extra beyond the contract. We examine the lawfulness of the demands.

Termination of the contract

In case of prolonged delay or substantial defects — refund of amounts paid with interest and losses.

Common property of a new building

Parking, storage rooms, and the adjoining territory: challenging conditions that restrict owners' rights.

Developer bankruptcy

Inclusion of claims in the register, protection of the buyer's rights, dealing with the administrator and other creditors.

Do not sign the acceptance certificate — first let a lawyer specialising in developer disputes review the documents

The first consultation is free. Often a well-drafted pre-action claim with a calculation is enough: developers prefer to pay extra rather than litigate publicly.

  • Delay in completion
  • Defects in the apartment
  • Dispute over the floor area

Cost

Prices for a lawyer's services in disputes with a developer

Indicative prices. The exact amount is quoted after reviewing the contract and the documents for the property.

Service What is included Cost
Contract consultation Review of the terms and assessment of the prospects of the dispute free of charge
Calculation of the penalty Calculation with justification based on the terms of the contract from 20,000 ₸
Assistance at handover Attendance at the inspection and recording of defects in the acceptance certificate from 45,000 ₸
Pre-action claim to the developer Demand for a penalty or for remedying defects from 35,000 ₸
Claim for recovery of the penalty Drafting a claim with calculations and annexes from 50,000 ₸
Conducting the case in court First instance on a turnkey basis, without your involvement from 170,000 ₸
Dispute over defects with expert examination Conducting the case with a construction and technical expert examination from 220,000 ₸
Termination of the contract and refund of money Full support until the funds are returned from 250,000 ₸

Prices are for reference only and do not constitute a public offer. The state fee and the construction and technical expert examination are paid separately.

How the dispute is handled lawyer for disputes with the developer

We read the contract

The handover deadline, the procedure for changing the area, the liability of the parties, the acceptance terms — all of this determines the amount of the claims.

We calculate the penalty

From the date specified in the contract to the actual handover. The amount usually surprises both parties.

Recording the defects

An inspection with a list of defects, photographs, measurements. The acceptance act must not be signed without comments.

Pre-trial claim

A demand with a calculation. Developers often pay before court to avoid setting a precedent for the building.

Contract with a fixed price

The scope of work and the cost are fixed in writing before the start.

Statement of claim

Recovery of the penalty, the cost of remedying the defects and losses, and, if necessary, an expert examination.

Hearings

We handle the case ourselves; the client's participation is usually not required.

Recovery

We support enforcement proceedings until the money is actually received.

Is the developer delaying handover?

Send us the contract and the correspondence — we will calculate the penalty from the exact date and prepare a claim.

Describe your situation

Team

Team of lawyers in Almaty

We handle a case from start to finish with the same team: you always know who is dealing with your matter and who to contact.

Asel Kurmanova — Lawyer for civil cases

Asel Kurmanova

Lawyer for civil cases

Handles disputes over real estate, inheritance, contracts and transactions. Supports transactions from document review through to registration of title.

  • 14 years of practice
  • Civil and housing disputes
  • Kazakh and Russian languages
Dmitry Kim — Lawyer for financial and motor vehicle disputes

Dmitry Kim

Lawyer for financial and motor vehicle disputes

Works with banks, insurers and debt collectors, handles recovery and bankruptcy cases, and defends drivers in administrative matters.

  • 11 years of practice
  • Banks, insurers, motor vehicle disputes
  • Pre-trial settlement
Gulnara Abisheva — Lawyer for family and social matters

Gulnara Abisheva

Lawyer for family and social matters

Handles divorces, division of property, alimony and disputes over children, as well as employment, pension and social issues.

  • 9 years of practice
  • Family and employment disputes
  • Work with guardianship authorities
Yerlan Sagintayev — Lawyer for corporate law

Yerlan Sagintayev

Lawyer for corporate law

Supports company transactions, arranges shares and corporate agreements, handles disputes between participants and reorganisation.

  • 13 years of practice
  • Transactions, shares, corporate disputes
  • Support for investment rounds
Aigerim Nurlanova — Tax lawyer

Aigerim Nurlanova

Tax lawyer

Challenges notifications and inspection reports, handles tax disputes in court, supports inspections and recovers overpayments.

  • 10 years of practice
  • Inspections and tax disputes
  • Working with the client's accounting records
Viktor Li — Construction and contract lawyer

Viktor Li

Construction and contract lawyer

Reviews contract agreements, estimates and acts, handles disputes over quality and scope of works, supports acceptance of facilities.

  • 12 years of practice
  • Contracting, shared participation, acceptance
  • Working with construction expertise
Madina Ospanova — Intellectual property and IT lawyer

Madina Ospanova

Intellectual property and IT lawyer

Protects copyright and trademarks, drafts contracts for IT teams and handles rights to products and code.

  • 8 years of practice
  • Copyright, trademarks
  • Contracts for IT and studios
Sanzhar Ibraev — Bankruptcy and debt recovery lawyer

Sanzhar Ibraev

Bankruptcy and debt recovery lawyer

Handles bankruptcy and rehabilitation procedures, recovers receivables, defends directors against subsidiary liability.

  • 15 years of practice
  • Bankruptcy, rehabilitation, debt recovery
  • S

Practice

Recent case stories from our lawyers in Almaty

Details have been changed and anonymised: the content of the case is protected by professional privilege.

Delay

The building was handed over fourteen months late

Situation
Under the contract, the apartment was to be handed over in December, but the keys were actually issued fourteen months later. All that time the family was renting housing and paying the mortgage at the same time. The developer referred to a clause on postponement of the deadline and offered a free storage room "as an apology".
What we did
We analysed the postponement clause: it allowed a shift, but required notification within a certain period and in a certain form, which the developer never did. We calculated the penalty for the entire period of delay and attached documents confirming the rental costs.
Outcome
The developer paid a penalty close to the calculated amount and compensated part of the rental payments. The dispute was closed by a pre-action claim within two months, without going to court.
Area

The actual area turned out to be 3.8 metres less than the design area

Situation
During the measurements before handover of the flat, it emerged that the area was almost four square metres less than stated in the contract. The developer claimed the discrepancy was within the permissible range and that no recalculation would be made.
What we did
We reviewed the contract terms on the permissible deviation and the recalculation procedure, and commissioned an independent measurement to confirm the actual area. We showed that the deviation exceeded the agreed limits and sent a demand for a refund of the difference based on the price per square metre.
Outcome
The difference was refunded in full. In addition, the developer paid for the independent measurement.
Handover and acceptance

The flat was handed over with unfinished work, and they offered the acceptance certificate for signing without any remarks

Situation
At acceptance, crooked walls, non-working ventilation and cracks in the screed were found. The developer's representative assured us that everything would be fixed, but the certificate had to be signed that day, otherwise 'the flat would go to the end of the queue for remedial work'.
What we did
We refused to sign the certificate without remarks and drew up a defects schedule with photographic evidence of each item and a reference to the relevant rooms. We sent it to the developer officially, demanding that the defects be remedied within a reasonable time and setting out the consequences of inaction.
Outcome
The defects were remedied within a month and a half, after which the flat was accepted without any remarks. The developer did not dispute a single item in the schedule.
Finishing

The flat was handed over with finishing that did not match the contract

Situation
Under the contract, the flat was to be handed over with a certain standard of finished finishing: laminate flooring, interior doors, sanitaryware with specific specifications. In fact, linoleum was laid, doors were installed made of a different material, and some of the sanitaryware was missing altogether. The developer suggested signing the certificate and 'sorting it out later'.
What we did
We did not sign the certificate; instead, we recorded the discrepancies in an annex to it, with photographs and references to the contract clauses. We commissioned an estimate to bring the finishing into line with the contract and sent a pre-action claim demanding either that the works be carried out or that their cost be reimbursed.
Outcome
The developer carried out works on three items and compensated 1.2 million tenge for the rest. The flat was accepted two months later, without any remarks.
Termination

Construction was frozen, and the buyer decided to get the money back

Situation
Construction stopped for almost a year: no work was carried out on the site, and the deadlines had already been postponed twice. The buyer, who had invested 14 million tenge, wanted to get the money back, but the developer offered only a transfer to another property in a remote area.
What we did
We checked the grounds for termination: the lengthy delay in handover gave the right to withdraw from the contract with a refund of the money paid and payment of a penalty. We sent a notice of withdrawal with a calculation, and at the same time checked the developer's financial position and filed a claim with an application for interim measures.
Outcome
We recovered 14 million in principal debt and 2.3 million in penalty. The freezing of accounts imposed on our application ensured that the money was actually received within five months.
Common property

The developer kept premises that formed part of the common property

Situation
After the building was commissioned, it emerged that the pram rooms and some of the technical premises had been registered as the developer's property and were being let out. The residents paid for the maintenance of the common property but could not use these premises, and access to the courtyard was restricted by a barrier with paid entry.
What we did
We analysed the design documentation: the disputed premises had been designated as common areas and had no independent purpose. We helped hold a meeting of the owners, drew up the minutes and prepared a claim for recognition of the right of common ownership over these premises.
Outcome
The right of common ownership was recognised, and the premises were transferred to the residents. Income from renting one of them now goes to the building's account and covers part of the maintenance costs.
Warranty

Two years after moving in, the roof started leaking, and the developer blamed it on use

Situation
Leaks appeared in the flats on the top floor. The developer claimed that the warranty period for the finishing had expired and that the cause was improper use of the roof by residents who installed antennas and air conditioners.
What we did
We distinguished between the warranty periods: for structural elements and the roof it is longer than for the finishing. We arranged a construction and technical expert examination, which established a breach of the roofing technology during construction. We sent a collective pre-action claim on behalf of the owners.
Outcome
The developer repaired the roof at its own expense and compensated the damage from the leaks in the flats — 3.4 million tenge for eight owners.
Unilateral act

The developer drew up a transfer act unilaterally and demanded payments

Situation
The buyer refused to accept the flat because of significant defects, recording them in writing. The developer drew up a unilateral transfer act, declared the property transferred and began charging maintenance payments, also claiming that the delay had ended on the date of that act.
What we did
We showed that a unilateral act is possible where the buyer unreasonably evades acceptance, not where there is a reasoned refusal listing defects. We gathered evidence: applications with acceptance stamps, photographs, and a specialist's report on the nature of the defects.
Outcome
The unilateral act was declared invalid, and the penalty was recovered for the entire period until the defects were actually remedied — 2.7 million tenge. The flat was accepted after the defects were remedied.

Useful information

Lawyer for disputes with developers in Almaty: deadlines, defects, floor area

People most often come to a lawyer for disputes with developers after the handover deadline has passed and the keys have not been issued: the developer postpones the date, cites approvals or suggests signing an addendum. Another ground is a flat accepted with defects, or an actual floor area smaller than stated in the contract. A third situation is an intention to terminate the shared construction agreement and recover the money paid.

Shared construction is governed by the Law of the Republic of Kazakhstan on Shared Participation in Housing Construction, and a developer may raise buyers' money only in the forms provided for by law. The article shows how a claim is formed at the pre-trial stage, which documents and technical findings underpin the position, how claims differ in cases of delay, defects, discrepancy in floor area and termination, and how enforcement of a judgment works. Specific amounts and payment procedure are determined separately.

When a lawyer for disputes with developers is needed: typical causes of conflict

Shared construction is governed by the Law of the Republic of Kazakhstan on Shared Participation in Housing Construction: a developer may raise buyers' money only in the forms provided for by law. The buyer has not an abstract promise but a set of rights secured by the contract and the law. Their violation grows into a dispute with the developer — a separate category of cases with its own specifics.

Delay in handover is the most common reason for seeking help. The property may be ready but not commissioned, or the transfer act is not signed without any explanation. The buyer is left alone with an organisation that has a staff of lawyers and a well-established scheme of objections.

The second group is the quality and characteristics of the property: defects in the flat, deviations from the design, and unfinished works require recording and a competent assessment. A discrepancy between the actual and designed floor area stands apart — it affects the contract price and requires recalculation.

The third scenario is refusal to terminate the contract and return what was paid. The developer cites formal grounds, delays replies and offers addenda instead of a refund. An early legal assessment matters here: it shows whether there are grounds for termination and how to structure the correspondence.

A lawyer for disputes with developers steps in when negotiations have reached a dead end and a position supported by documents is needed. The work follows this logic:

  • Review of the shared construction agreement, its annexes and correspondence with the developer.
  • Recording violations: deadlines, defects, deviations in area.
  • Preparing and sending a pre-action claim with a calculation of demands.
  • Collecting evidence: reports, specialist opinions, correspondence.
  • Protecting the buyer's interests in court under the rules of the Republic of Kazakhstan.
  • Supporting enforcement of the judgment after it enters into force.

What a lawyer does in disputes with a developer at the pre-trial stage

The pre-trial stage in disputes with a developer is about gathering the evidence base that determines which claims can be substantiated. The lawyer starts by analysing the shared construction participation agreement: checking the deadline for handover of the property, the procedure for changing it, the terms on quality, warranty obligations, acceptance and jurisdiction. This is where the terms by which the developer tries to limit its liability become visible.

Next, the correspondence with the developer is reviewed: notices of postponement of the deadline, proposals to sign addenda, responses to enquiries. Acceptance and inspection reports and specialist opinions on defects are compared. Violations are recorded — delay in handover, deviations from the design documentation, discrepancy between the actual area and the contractual area. For a breach of the handover deadline, the buyer is entitled to claim a penalty under the contract and the law, but the calculation must rely on confirmed dates and documents.

The pre-action claim procedure is the next step. In the claim, the demands are formulated precisely: with reference to the terms of the contract, to the provisions of the Law of the Republic of Kazakhstan on shared participation in housing construction, with the calculation and copies of documents attached. The document records the buyer's position before court, and sometimes leads to voluntary rectification of defects or payment. If the dispute reaches court, the pre-trial work determines which evidence will form the basis of the judgment.

Work at the pre-trial stage includes:

Delay in handover of an apartment: how a lawyer in disputes with a developer builds the claim

A dispute over delay in handover of an apartment is built on comparing two dates: the deadline under the shared construction participation agreement and the date of actual handover. Until the apartment is handed over under an acceptance report, the developer's obligation is not considered fulfilled, even if the building is ready. A lawyer in disputes with a developer checks the contract, the design documentation and the construction permit to determine the moment by which handover was required to take place.

The period of breach is calculated from the agreed date to the day the report is signed. It determines the scope of the claim and serves as the basis for calculating the penalty under the law on shared participation. If the developer proposes to change the deadline by an addendum after it has passed, an assessment is made of whether the change was voluntary and whether it was connected to a known lag in the works.

The developer may refer to circumstances exempting it from liability: force majeure, material change of circumstances, fault of the contractor organisations or actions of the buyer who delayed acceptance. Each ground requires documentary confirmation and a causal link to the delay. The disputes come down to checking whether the breach depended on the developer's will and whether it could have been prevented.

  • Compare the handover date under the contract with the date of signing the acceptance report.
  • Determine the period of delay and check whether the deadline was changed by addenda.
  • Check the grounds for exempting the developer from liability and their documentary confirmation.
  • Record defects in the acceptance report and assess warranty obligations after handover of the apartment.

Defects in a new building: what a buyer brings to a lawyer in disputes with a developer

Defects in a new building are divided into structural, engineering, finishing and operational. Structural ones concern load-bearing elements, walls, floors, roofing, foundation: cracks, sagging, freezing. Engineering ones relate to heating, water supply, sewerage, ventilation, electrics: leaks, lack of pressure, wiring defects. Finishing ones cover the screed, plaster, windows, doors, coatings. Operational ones are identified during occupation: damp, noise, non-working ventilation.

Recording begins with the inspection at acceptance: remarks are entered in the report, and refusal to sign without an inspection deprives the buyer of the ability to prove the defect. If the developer evades a joint inspection, defects are recorded with an independent specialist, with photo and video recording, and the design and as-built documentation is requested for comparison with the design solution. For latent defects, the law links the moment of their discovery to the moment the buyer learned of them.

The key distinction is between remediable and substantial defects. Remediable ones do not affect the use of the premises for its purpose: they can be fixed without disproportionate costs and loss of strength. Substantial ones make the property unfit for habitation or require disproportionate expense and time. The classification determines the scope of the claims: from rectification and proportionate reduction of the price to refusal of the contract and termination.

  • Structural — load-bearing structures, walls, floors, roofing, foundation.
  • Engineering — heating, water, sewerage, ventilation, electrics.
  • Finishing — screed, plaster, windows, doors, coatings.
  • Operational — dampness, noise, freezing, non-working ventilation.
  • Latent — discovered after occupancy or when structures are opened up.
  • Area — a discrepancy between the actual area and the contractual area entails a recalculation under the terms of the contract.
Defects and their legal significance
Type of defect Criterion Consequence
Remediable Can be fixed without disproportionate costs Claim for rectification
Substantial The property is unfit or the costs are disproportionate Repudiation of the contract, termination
Latent Discovered after acceptance The period runs from the moment of discovery
Area Discrepancy with the contractual figure Recalculation under the terms of the contract

The scope of claims is determined by the nature of the defect and the terms of the contract.

The area of the flat is less than the contractual area: a lawyer's position on disputes with the developer

The actual area of a flat in Kazakhstan is determined on the basis of a technical survey by a licensed organisation. Measurements are taken along the internal surfaces of the walls: living rooms and utility rooms are included in the total area, while loggias, balconies and verandas are included with reduction coefficients. The result is recorded in the technical passport, which the developer hands over together with the keys. It is this document, and not the design documentation, that confirms the actual area.

A discrepancy between the design area and the actual area does not in itself always mean a breach of contract: a minor deviation is permissible and is due to the nature of construction work. A ground for recalculation arises when the difference goes beyond the permissible deviation, worsens the consumer properties of the flat or increases the contract price.

In the event of a substantial discrepancy, the purchaser is entitled to demand a proportionate reduction of the contract price or the rectification of defects. If the developer refuses to recalculate the price voluntarily, the dispute is referred to court. In the event of a substantial delay, the purchaser is entitled to terminate the contract and demand a refund — the mechanism also applies where the flat has been handed over with departures from the terms of the contract.

  • checking the design area stated in the contract against the actual area according to the technical passport
  • verification of permissible deviations provided for by the contract and construction norms
  • assessment of how the discrepancy affects the contract price and the consumer qualities of the apartment
  • analysis of the contract terms on the recalculation procedure and the developer's unilateral acts
  • recording the developer's refusal to voluntarily reduce the price or remedy the defects
  • preparation of a pre-action claim and a statement of claim with a calculation of the claims asserted

In disputes with a developer, the outcome is decided not by emotion but by the recorded discrepancy between the contract and what was actually handed over to the participant in shared construction.

Termination of a contract with a developer: when a disputes lawyer supports such a claim

A participant's unilateral withdrawal from a shared construction participation agreement is possible where the developer breaches the deadlines for handing over the object or makes substantial departures from the design. The right to withdraw also arises where construction is suspended or the volume of works is reduced, if this indicates that the object will not be handed over within the agreed timeframe. A lawyer handling disputes with a developer checks whether notice of withdrawal was given in writing and whether the procedure for its delivery was observed: the moment of termination depends on this.

Termination through the court is required where the developer does not accept the withdrawal or the parties have not reached agreement on ending the contract. The ground is a material breach of the terms: systematic delay, unremedied defects, discrepancy in area. The court assesses the conduct of both parties and the extent to which the participant itself performed its counter-obligations.

The position is strengthened by documented facts of the breaches, correspondence with the developer, a specialist's report on the defects and the absence of counter-delay on the participant's side. Termination is risky if payment was not made in full, the object was in fact accepted without reservations, or the breaches are remediable. The developer's bankruptcy requires particular attention: participants' claims are included in the register in the established procedure, and termination of the contract does not always improve the position.

  • Delay in handing over the object against the agreed deadline
  • Substantial departure from the design documentation
  • Suspension of construction or reduction in the volume of works
  • Unremedied defects making the object unfit for use
  • Discrepancy between the actual area and the area paid for
  • Incomplete payment or acceptance of the object without reservations on the participant's side

Which disputes lawyer with a developer conducts a case in the court of Almaty

Disputes with a developer in Almaty are heard under the rules of jurisdiction — at the location of the defendant or at the place of performance of the shared construction participation agreement. If the object is in Almaty, the case as a rule goes to the Specialized Interdistrict Economic Court or a district court — depending on the nature of the claim and the status of the parties. A disputes lawyer with a developer builds the position from day one so that it matches the evidence base that the court of Almaty actually examines in housing and construction cases.

The composition of the evidence is of key importance: the shared participation agreement, the acceptance certificate, correspondence with the developer, payment documents, technical documentation for the object, and the results of measurements. The courts of Almaty do not accept unsubstantiated arguments about defects — either defects recorded during an inspection or a specialist's report are required. That is why support begins with recording the breaches before going to court, not after.

Expert examination is the central element of proof: a construction and technical expert examination establishes the existence and cause of the defects, and in a dispute over area — the actual area of the object according to measurements. The representative must formulate the questions to the expert correctly and assess the expert's report, since the outcome of the case depends on this. The difference between the developer's offer and what was recovered by the court reached six times — this shows how much the position in the proceedings affects the result.

Comparison of a participant's claims: what a disputes lawyer with a developer asserts

A dispute with a developer rarely comes down to a single claim. Shared participation is governed by the Law of the Republic of Kazakhstan on Shared Participation in Housing Construction, and a developer may raise participants' money only in the forms provided for by law. Hence the set of claims that a participant asserts simultaneously or in turn. A disputes lawyer with a developer determines which of them are compatible in one set of proceedings and which compete with each other.

Delay in handover gives the right to a penalty for the period of the breach and to compensation for losses not covered by the penalty. Defects in the apartment give rise to a claim for their free-of-charge remedy, a proportionate reduction in price or reimbursement of the costs of putting them right. A shortfall in area according to measurements allows a proportionate reduction in price to be claimed, and where the deviation is substantial — withdrawal from the contract. Termination returns the parties to their original position and entails the return of the money paid.

The compatibility of claims is determined by their basis. A penalty for delay and the remedy of defects arise from different breaches and are asserted together. A reduction in price due to a shortfall in area and the remedy of defects are also compatible if they concern different defects of the object. Termination of the contract excludes further claims under the same contract: instead of performance in kind, the participant receives a return of the money. One cannot simultaneously claim handover of an apartment with the defects remedied and termination of the contract on the same ground.

  • penalty for breach of the deadline for handing over the object — for the period of delay
  • compensation for losses not covered by the penalty
  • free-of-charge rectification of defects in the flat
  • proportionate reduction of the price due to defects or shortfall in area
  • reimbursement of the purchaser's costs of rectifying defects at their own expense
  • termination of the contract with return of the money paid
What goes with what
Claim Ground Goes with Excludes
Penalty for delay Breach of the handover deadline Rectification of defects, reduction of price —
Rectification of defects Defects in the flat Penalty, reduction of price —
Reduction of price Defects or shortfall in area Penalty, rectification of defects —
Reimbursement of costs Purchaser's costs of rectification Reduction of price —
Termination of the contract Material breach Return of money Transfer of the apartment, rectification of defects

Claims for termination and for specific performance of the contract are mutually exclusive in a single claim.

Evidence in disputes with a developer: what a lawyer in developer disputes collects

The buyer's position rests on written documents. The foundation is the agreement on shared participation in construction with its annexes: the works schedule, description of finishes, layout. Attached to it are payment documents: payment orders, receipts, bank statements, and receipts for direct settlements. They confirm that the buyer has performed its obligations and has the right to demand counter-performance.

The second layer is documents on acceptance and the condition of the object. The acceptance-transfer deed records the date of actual transfer, from which the period of delay is counted: for breach of the deadline for transferring the apartment, the buyer is entitled to claim a penalty under the contract and the law. Defects identified during inspection are recorded in an inspection report or a defects report listing the works and materials to be replaced. Without such a document, any discussion of quality becomes a dispute over words.

The third block is correspondence and pre-action work. Letters, applications and notices sent through the records office or by post with an inventory of contents show that the developer knew of the claims and could have satisfied them voluntarily. Correspondence in messengers and by email is admissible, but its value is lower without confirmation of authorship and the sender's authority. A lawyer in developer disputes builds a chronology of communications so that each claim has documentary support.

  • the agreement on shared participation with all annexes and supplementary agreements
  • payment documents confirming full or partial payment
  • the acceptance-transfer deed or an inspection report listing the defects identified
  • correspondence with the developer and pre-action claims with proof of sending
  • a construction and technical expert report on the scope and cost of the defects
  • a report on the discrepancy between the actual area of the apartment and the design area

Expert examination and inspection: how a lawyer in developer disputes uses technical findings

A construction and technical study in developer disputes confirms the existence of a defect and translates an everyday description of the problem into measurable characteristics. Defects are recorded in the report at acceptance — that is the starting point. If a defect is not reflected in the report, its existence after transfer of the apartment is confirmed within the warranty period. A lawyer in developer disputes organises the work so that the technical finding forms the basis of the claim rather than remaining a reference document.

As regards a discrepancy in area, the expert examination establishes the actual area and compares it with the design and contractual area. Where the difference exceeds the permissible limits, the buyer has the right to a proportionate reduction in price or to a refund of the overpayment. Without measurements, the dispute comes down to an exchange of letters. The report turns the discrepancy into a verifiable fact for the developer and the court.

As regards the quality of works, the study answers as to the cause of the defect, its nature and whether it can be rectified. A substantial defect, one that is irremediable or recurs, affects the choice of claim — from rectification of the works and recovery of expenses to termination of the contract. The finding on cause is important for responding to the developer's objections that the buyer misused the property or caused the defect.

  • Recording defects in the acceptance report or within the warranty period
  • Measuring the premises and comparing the actual area with the design and contractual area
  • Determining the cause, nature and substantially of the defect
  • Assessing whether and how the defect can be rectified
  • Notifying the developer of the time and place of the inspection
  • Using the findings to calculate the scope of claims and to respond to the developer's arguments

A settlement agreement in developer disputes: when a lawyer in developer disputes recommends one

A settlement agreement under an agreement on shared participation in construction is appropriate where the developer acknowledges the breach and is ready to remedy it without dragging out the process. In cases of delay in transferring the object, additional payment for a reduction in area or replacement of substandard materials, the parties set out the procedure and close the conflict faster than a court of first instance would hear the case. For the buyer, this saves time and makes it possible to obtain the object or have the defects rectified in the agreed form.

A lawyer in developer disputes recommends a settlement agreement where the developer's position is strong and the buyer's claims are supported by documents. A court judgment is more advantageous if the developer evades, disputes the very fact of the breach or offers terms that do not reflect the scope of the obligation: the compulsory route yields a writ of execution and the possibility of applying to a court enforcement officer, whereas a settlement agreement depends on the good faith of the party.

Particular attention is required where the actual area differs from the contractual area: this triggers a recalculation under the terms of the contract. If the agreement does not describe this recalculation, the purchaser risks agreeing to a final figure that does not match the measurement. It is also unacceptable to waive further claims in respect of defects that have not yet been identified during the inspection.

Enforcement of a judgment in disputes with a developer: the role of a lawyer in disputes

A judgment handed down in a dispute with a developer does not by itself return any money. Once the act enters into legal force, the lawyer handling the dispute with the developer obtains a writ of execution from the court, checks that the details of the debtor and the claimant are correct, and submits the document for compulsory enforcement. The court enforcement officer initiates enforcement proceedings and sends requests to banks, registration authorities and tax authorities to establish the developer's accounts, property and receivables.

The work that follows is monitoring the progress of the proceedings, not a one-off instruction. The lawyer tracks the deadlines for enforcement actions and files motions to seize accounts and property, to restrict the disposal of the debtor's assets, and to obtain information that the enforcement officer has not requested on their own initiative. Where there is inaction, a complaint is filed with a superior authority or an application is made to the court to challenge the actions.

If the developer has insufficient funds, the order of priority and the challenging of transactions that moved assets out matter. Where there is a material breach of deadlines, the purchaser is entitled to terminate the contract and demand a refund, so enforcement may run in parallel with challenging the transfer of the property or with termination. Disputes with a developer are rarely limited to a single court stage, and it is enforcement that shows whether the infringed right has actually been restored.

  • obtaining the writ of execution and checking its contents
  • submitting the document to the court enforcement officer and initiating proceedings
  • requests concerning the developer's property, accounts and receivables
  • motions to seize assets and restrict the disposal of assets
  • challenging the inaction or unlawful actions of the enforcement officer
  • reconciling the amounts received with the amounts awarded and monitoring the closure of the proceedings

Reviews

Reviews of disputes with developers

4.9
Google
4.9  · 128
Yandex
4.8  · 94
2GIS
4.9  · 156
Zoon
4.7  · 41
Aliya T.

When the house was handed over 11 months late, I already understood they wouldn't just get away with it, but I didn't know where to start. The developer offered an air conditioner as a gift, and I almost agreed. Asel asked: did you count how much they underpaid you? Turned out the sum was many times bigger than any air conditioner. They calculated the penalty, filed with the court. We recovered through the court a sum many times bigger than what they offered. Thank you for stopping me back then.

Service: Lawyer for disputes with a developer in Almaty

Roman K.

The lawyer went with me to the handover. We found 23 defects including ventilation that didn't work at all, everything was entered into the report. They fixed it at the developer's expense.

Service: Lawyer for disputes with a developer in Almaty

Company response

Thank you for trusting us with the handover. Glad all the defects were fixed before signing.

Zhanar B.

When I got the keys and started taking measurements, I realized something was off. The area turned out to be 4.2 meters smaller, and that's even though I paid for a bigger one. At first I didn't even understand where to go and who to talk to. A friend advised me to go to these lawyers, because the developer wasn't answering calls. I went to the office several times, but there they just brushed me off with general words. The lawyer asked for the documents, read everything carefully and said a claim with a calculation was needed. They did the calculation, sent it, and I was already preparing for court. But the developer returned the difference without court. The claim with the calculation was enough. Very grateful for the calmness and precision.

Service: Lawyer for disputes with a developer in Almaty

Sergey P.

My husband and I went to see the new apartment, the developer sent a paper saying we had to pay extra for the extra meters. But according to the measurements those meters didn't exist at all. I didn't understand what to do myself, so I went to the lawyers. They sorted it out, the extra charge was removed. Thank you very much.

Service: Lawyer for disputes with a developer in Almaty

Dinara M.

I signed the acceptance report without any remarks right after the handover, didn't even think it was possible. Then a few months later cracks started appearing on the walls, and I realized I couldn't figure this out without a lawyer anymore. I looked for someone who actually works with cases like this, not just gives consultations. They honestly told me the chances were lower, because the report was already signed. But I was ready for any outcome. They did an expert examination, confirmed it was a construction defect. Part of the repair cost was still recovered through the expert examination. Not all of it but a big part. Very grateful for the honesty.

Service: Lawyer for disputes with a developer in Almaty

Ainur Zh.

The developer went bankrupt, the claims were included in the register. We're still waiting, but the lawyer explained the whole procedure.

Service: Lawyer for disputes with a developer in Almaty

Company response

Thank you for your trust. We continue to monitor the process and will let you know as soon as there is any information.

Marat N.

The handover was delayed by eight months. I went to the lawyers because the developer was offering ridiculous compensation, Madina said that by law more was owed. The penalty turned out to be more than all the compensation the developer was offering

Service: Lawyer for disputes with a developer in Almaty

Olga T.

At the inspection they found twenty issues. Sanzhar was there and put everything into the report. They fixed them before signing, though we had to wait longer for their response than we would have liked. In the end everything was fine

Service: Lawyer for disputes with a developer in Almaty

Yerzhan B.

they tried to talk me into signing the report without any issues and promised a fridge, good thing I didn't give in. I came to the lawyers because I felt something was off here. They laid it all out clearly

Service: Lawyer for disputes with a developer in Almaty

Aigul Zh.

I got the apartment, and the area turned out to be smaller than the project. I didn't know what to do about it, so I went to the lawyers. They returned the difference.

Service: Lawyer for disputes with a developer in Almaty

Sergey K.

When I realized my house was handed over later than the deadline, I started looking for a lawyer because I didn't know how to correctly calculate the penalty myself. The developer started offering to sign an additional agreement about postponing the deadline. I didn't immediately understand what that actually meant. They explained to me that if I signed, I would give up the penalty. Good thing I asked before signing. I didn't sign. Then we started working with the lawyer and everything went differently. Of course there were some nerves, but there is a result. Thank you for the clear explanation

Service: Lawyer for disputes with a developer in Almaty

Natalya M.

I spent more than two years waiting for my flat from the developer and was completely worn out. I went to them myself several times about cancelling the contract, but they just dragged it out and never gave a straight answer. So I decided to go to a lawyer. They sorted out all my documents and prepared a claim. In the end I got my money back with interest. Thank you for helping me in such a difficult time.

Service: Lawyer for disputes with a developer in Almaty

Daniyar S.

When I got the flat I noticed there were a lot of defects in the interior finishing work, there were cracks in the screed. Since I didn't understand it myself, I contacted Aigerim and asked for advice. She checked everything carefully and said an expert examination was needed. The examination confirmed it, and they fixed the defects at their own expense. Thank you.

Service: Lawyer for disputes with a developer in Almaty

Company response

We are glad we could help. Getting the defects fixed is the main thing.

Irina V.

When the house was handed over with a big delay, I couldn't figure out for a long time what to do and where to turn. The developer kept feeding me promises, and then stopped answering calls altogether. A friend gave me a lawyer's contact, and I decided to try. They explained in detail how the penalty is calculated and what documents are needed. We filed a claim, and I was very worried that the court would reduce the amount. But the penalty was recovered in full, the court didn't reduce it. I am very grateful for the work. Without a lawyer I definitely wouldn't have managed

Service: Lawyer for disputes with a developer in Almaty

Talgat R.

They assessed the risks of terminating honestly: they said the developer has problems and you might not even get your money. We decided to wait for the building.

Service: Lawyer for disputes with a developer in Almaty

Svetlana D.

the windows leaked from day one, they refused under warranty. Sanzhar helped draft a claim and through it they replaced them

Service: Lawyer for disputes with a developer in Almaty

Bekzat A.

The ventilation didn't work in the whole stairwell. A collective complaint worked.

Service: Lawyer for disputes with a developer in Almaty

Yelena P.

It took a while, but it got done. They explained every step, though sometimes you have to wait for Dmitry's response. But I'm happy with the result

Service: Lawyer for disputes with a developer in Almaty

Company response

Thank you for noting that. Maintaining stable communication with clients is our priority.

Kairat Sh.

They helped with the inspection of the second apartment, already as a regular client. They found even more issues

Service: Lawyer for disputes with a developer in Almaty

Company response

Thank you for coming back to us. Glad that the second inspection also went well.

Asel G.

The developer demanded an extra payment for the extra square meters, but there was no such condition in the contract, we fought it off

Service: Lawyer for disputes with a developer in Almaty

Company response

Thanks for the review. Good that we managed to resolve the issue.

FAQ

Can I refuse to sign the acceptance report?

Yes, if there are defects. They are recorded in the report or in a separate list. Signing «without comments» on an oral promise to fix things later is the most costly mistake a buyer can make.

How is the penalty for delay calculated?

From the handover date under the contract to the actual handover under the report, at the rate provided for by the contract and the law. We prepare the calculation at a free consultation.

The developer sent a supplementary agreement to postpone the deadline

You are not obliged to sign it. Signing means agreeing to the new deadline and waiving the penalty for that period.

The floor area turned out to be smaller than the design area

The difference is refundable. The basis is the measurements and the contract terms on how to settle a discrepancy in floor area.

Defects were found after the acceptance report was signed

Claims are still possible within the warranty period, but they are harder to prove: an expert examination will be needed to confirm that the defect is construction-related.

How long does a dispute with a developer last?

The pre-action stage takes up to a month. Court proceedings usually take three to five months, longer with an expert examination.

Should I terminate the contract if there is a delay?

Sometimes yes, but first we assess the developer's financial position: obtaining a judgment and actually getting the money are two different things.

The developer has gone bankrupt, what should I do?

File claims in the insolvency proceedings and protect the buyer's rights through the register of creditors. The earlier this is done, the better the chances.

How much do lawyer's services cost for disputes with a developer?

The consultation is free. A lawyer attending the handover is charged separately from handling the penalty claim. A construction expert examination, if needed, is paid for separately.

Can we discuss a dispute with a developer online?

Yes. Send the contract, notices of postponed completion dates and photos of defects via WhatsApp — they show what can be claimed.

Should I sign a supplementary agreement postponing the completion date?

Usually not: by signing it, you voluntarily waive the penalty for the entire period of delay. Before signing, calculate how much you are giving up.

Contacts and maps

Where to find a lawyer for disputes with a developer in Almaty

Address
1 Abylai Khan Ave, Almaty
Appointments
at the office and by video call, visits around the city
Working hours
Mon–Sun: 10:00–19:00

2GIS opens in a separate tab — the service does not allow embedding an organisation card.

Open in 2GIS

Zoon opens in a separate tab: client reviews and ratings are there.

Open on Zoon

Tell us about your situation

The first consultation is free. If the matter can be resolved without court, we will say so directly.

WhatsApp Call